Biographical information
This page gives a summary of the main points of my professional life, including education, employment, and a selection of bridge design projects to which I have contributed.
My complete curriculum vitae can be downloaded in .pdf format.
More detailed information on my current activities can be found in the teaching, research, and consulting sections of this site.
Dr.sc.techn. |
1993 |
Federal Institute of Technology (ETH) |
M.S.E. |
1983 |
Princeton
University |
B.Sc. |
1981 |
University of Victoria |
Since 2014 |
Professor |
Department of
Civil Engineering |
Since 2002 |
Associate Professor |
Department of
Civil Engineering |
1997 to 2002 |
Principal |
J. Muller International |
1996 to 1997 |
Senior Structural Engineer |
VSL Corporation |
1993 to 1996 |
Senior Engineer |
Buckland and Taylor
Ltd. |
1990 to 1992 |
Research Associate |
Professor Christian Menn |
1990 |
Senior Engineer (Structures) |
|
1987 to 1989 |
Research Associate |
Professor Christian Menn |
1985 to 1987 |
Project Engineer |
Morrison Hershfield Ltd. |
1983 to 1985 |
Design Engineer |
T.Y. Lin
International |
This is a sample of some of the design projects to which I have contributed. More information on these projects as well as additional projects can be found in my CV and in the section on my consulting activities.
Pont Laviolette Redecking Feasibility Study, Trois-Rivières to Bécancour, QC, Canada
I
was retained by the prime consultant to develop preliminary concepts for
replacement of the concrete deck slab on a 2 700 m long, four-lane crossing
of the St. Lawrence. The owner limited work on the deck to the closure of
two lanes between 9:00 PM and 6:00 AM every night. This severe constraint
led to solutions that incorporated large precast post-tensioned concrete
panels that were designed and detailed to allow them to carry full design
live load immediately after they had been erected. An innovative system of
temporary external post-tensioning was developed for the longitudinal steel
girders on the approach spans.
BQE Connector Ramp to Williamsburg Bridge, Brooklyn, NY, USA
I
was Principal in Charge of this project, responsible for all major design
decisions and oversight of project staff. The scope of work was to replace
an aging four-lane, 400 metre long steel viaduct passing through a densely
populated neighbourhood. The structure is a primary commuter route linking
Brooklyn to Manhattan. Because no new right of way could be acquired, it was
necessary to locate the new structure along the same alignment as the
existing viaduct. The total duration of lane closures during construction
was minimized by building the superstructure in two parallel halves, which
allowed two lanes of traffic to be maintained at all times during
construction, and through the use of the precast segmental method of
construction, which allowed the superstructure to be built at an average
rate of one complete span per week.
Bridge across Rocky Creek, Monterey County, CA, USA
I
was Lead Designer for this project, and was responsible for all major design
decisions. The scope of work was to design a seismic retrofit of a
reinforced concrete arch bridge originally built in the 1930s. Technical
challenges included the proximity of the bridge to a major fault, which
resulted in peak rock accelerations in excess of 0.7g, as well as the
vulnerability of the relatively slender arch ribs. The solution was based on
the provision of an alternate load path which ensured that inertial forces
from the deck were not transferred to the arch. This was accomplished by
post-tensioning the deck longitudinally to increase its stiffness and
strengthening the abutments to ensure that they had adequate capacity to the
higher seismic forces that would be imposed on them by the stiffened deck.
Royston Road Underpass, Vancouver Island, BC, Canada
I
was Lead Designer for this project, and was responsible for all major design
decisions. The scope of work was to design a new overpass crossing a new
four-lane highway. Because maintenance of traffic during construction was
not an issue, a reinforced concrete post-tensioned rigid frame bridge was
proposed. Compared to conventional solutions (two-span structures with
precast concrete I-girders), the proposed solution offered the following
advantages: (1) greater safety for motorists due to the absence of a pier in
the median of the mainline highway, (2) enhanced durability due to a smaller
surface of concrete exposed to salt spray, and (3) a higher standard of
aesthetic design.
January 24, 2015 | © 2015 Paul Gauvreau